A company's production process involves a series of operations: cutting, drilling, and assembly. If the cutting operation takes 2 hours, the drilling operation takes 3 hours, and the assembly operation takes 4 hours, what is the total production time?

Answer Options

A. 9 hours
B. 10 hours
Correct Answer C. 11 hours
D. 12 hours
Correct Answer
C
Correct Option:
11 hours

About This Question

This is Post Utme Crawford University 2023 Commerce Question 14. It is one of the objective questions from the 2023 Post Utme Crawford University Commerce examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support