A company is considering the construction of a new factory in a region prone to landslides. What is the primary environmental issue that the company should consider?

Answer Options

Correct Answer A. Soil erosion
B. Water pollution
C. Air pollution
D. Noise pollution
Correct Answer
A
Correct Option:
Soil erosion