Post Utme Coal City University 2023 General Studies Question 36

Practice objective / multiple choice question 36 from the 2023 Post Utme Coal City University General Studies examination.

Post Utme Coal City University 2023 General Studies Objective / Multiple Choice
Question 36 POST_UTME_COAL_CITY_UNIVERSITY • 2023 • GENERAL STUDIES • objective

A company is considering investing in a new project that has a cost of ₦500,000 and a benefit of ₦750,000. What is the net present value (NPV) of the project?

Answer Options

A. ₦125,000
B. ₦250,000
Correct Answer C. ₦375,000
D. ₦500,000
Correct Answer
C
Correct Option:
₦375,000

About This Question

This is Post Utme Coal City University 2023 General Studies Question 36. It is one of the objective questions from the 2023 Post Utme Coal City University General Studies examination.