A company uses the percentage of completion method to value its construction contracts. The company has a contract with a total value of ₦1,000,000 and has completed 75% of the work. What is the value of the contract?

Answer Options

A. ₦750,000
B. ₦800,000
C. ₦850,000
Correct Answer D. ₦900,000
Correct Answer
D
Correct Option:
₦900,000