Tani Kamac (TK) makes three products A, B, and C. All the three products must be offered for sale each month in order to be able to provide a complete market service. The products are fragile and their quality deteriorates rapidly once they are manufactured. The products are produced on two types of machine and worked on by a single grade of direct labour. Five direct employees are paid ₦80 per hour for a guaranteed minimum of 160 hours each per month. All the products are first moulded on machine type 1 and then finished and sealed on a machine type 2. The machine hours requirements for each of the products are as follows: Product A: Machine type 1 - 1.5 hours per unit, Machine type 2 - 1.0 hours per unit; Product B: Machine type 1 - 4.5 hours per unit, Machine type 2 - 2.5 hours per unit; Product C: Machine type 1 - 3.0 hours per unit, Machine type 2 - 2.0 hours per unit. The capacity of the available machines type 1 and 2 are 600 hours and 500 hours per month respectively. Details of the selling prices, unit costs and monthly demand for the three products are as follows: Product A: Selling price - 910, Component cost - 220, Other direct material cost - 230, Direct labour cost at ₦80 per hour - 60, Overheads - 240, Profit - 160, Maximum monthly demand (units) - 120; Product B: Selling price - 1,740, Component cost - 190, Other direct material cost - 110, Direct labour cost at ₦80 per hour - 480, Overheads - 620, Profit - 340, Maximum monthly demand (units) - 70; Product C: Selling price - 1,400, Component cost - 160, Other direct material cost - 140, Direct labour cost at ₦80 per hour - 360, Overheads - 520, Profit - 220, Maximum monthly demand (units) - 60. Although TK uses marginal costing and contribution analysis as the basis for its decision making activities, profits are reported in the monthly management accounts using the absorption costing basis. Finished goods inventories are valued in the monthly management accounts at full absorption cost.
Additional Information
{ "label": "Supporting information 1", "content": "| | Product A | Product B | Product C |\n|---------------|-----------|-----------|-----------|\n| Machine type 1| 1.5 | 4.5 | 3.0 |\n| Machine type 2| 1.0 | 2.5 | 2.0 |" }

Requirements

( a )
Calculate the machine utilisation rate per month for each machine and explain which of the machines is the bottleneck/limiting factor.
( b )
Using the current system of marginal and contribution analysis, calculate the profit maximising monthly output of the three products.
( c )
Explain why throughput accounting might provide more relevant information in TK's circumstances.
( d )
Using a throughput approach, calculate the throughput-maximising monthly output of the three products.
( e )
Explain the throughput accounting approach to optimising the level of inventory and its valuation. Contrast this approach to the current system employed by TK.
( f )
Explain the importance of identifying scarce resources when preparing budgets and the use of linear programming to determine the optimum use of resources.

Detailed Solution & Marking Scheme

Get the step-by-step solution, key points required by examiners and detailed marking guidance through the Edcrib AI Tutor.

Reveal Answer

About This Question

This is Ican 2024 Performance Management Question 1. It is one of the mixed questions from the 2024 Ican Performance Management examination.

Master the Exam!

You've seen a preview, but there are thousands more questions plus AI tutor to break down complex solutions.

Unlock Full Access Available for Android & Windows
Chat with Support